The project consisted in the execution of a feasibility study for the identified opportunity of installing one small hydro-power plant at the village of Mfereke, Njombe Region, Tanzania.
The project consisted in the execution of a feasibility study for the identified opportunity of installing one small hydro-power plant at the village of Mfereke, Njombe Region, Tanzania.
The impact of this project was the availability of a fully-fledged bankable project proposal that, when executed, will provide: an additional 650.000 kWh/year of renewable energy and over 500 rural connections to households (450), local enterprises (50), public services (3), one corporate customer and the Professional College of Njombe.
Tanzania
EUR 59 287
EUR 49 873
Hydropower
Feasibility
2013 - 2014